Twin tunnels supplement Singapore canal

5 November 2018


Singapore – Herrenknecht recently released a report on the successful completion of a drainage tunnel in Singapore. The project, which broke through in December 2017, required the construction of 1,000m-long twin tunnels with an excavated diameter of 5,250mm.

The Herrenknecht EPBM supplied to the project worked its way through complex ground conditions, including highly weathered granite. Once it had completed the first drive, it was returned to the 24m-diameter launch shaft to begin the second.

Tiong Seng Contractors had to navigate a winding alignment with very little distance between the two tunnels and curve radii of 180m. Performances of up to 18m per day and 91m per week were achieved.

The project will expand the existing drainage system, the Stamford Canal, and reduce the chance and severity of flooding in the area.